Shoshone Water Treatment Plant
(on Placer Creek 1-mile outside town)
TEL: 208-752-1174
Plant Operators:
Dale Newell
Carl Shields
East Shoshone County Water District
606 Cedar St.
Wallace ID 83873
George Dancer, Water District Manager
TEL: 208-752-1174
Phil Boyd
Welch Comer & Associates, Inc.
1626 Lincoln Way
Coeur D'Alene ID 83814
TEL: 208-664-9382
Randolph L. Truby, Vice-President
Koch Membrane Systems
10054 Old Grove Road
San Diego, CA 92131
Tel: (619) 695-3840
Fax: (619) 695-2176
1-800-565-4369
Web Page: http://www.kochmembrane.com
| Startup Year | 1998 |
| Process | UF |
| Capacity (MGD) | 1.2 |
| Recovery Rate (%) | 80 |
| Pretreatment | filtration from stream with 50 micron screen |
| Post-Treatment | chlorine |
| Feed Water Composition | IW |
| Product Water Composition | DW |
| Concentrate Disposal | treatment tank followed by settling lagoon |
*The Mullan Water Treatment
Plant (0.8MGD) has the same data as the above table and same plant
operators, was built at the same time, and is located 7 miles east.
The larger town, Wallace, has a population of approximately 800.
Initially, the design rated capacity of the Shoshone Water Treatment Plant
was 2.0 MGD. Both plants utilize Koch hollow fiber membranes in a 4-stage
mode (Wallace) and 3-stage (Mullan).

The Romicon® Hollow Fiber membranes are
anisotropic (asymmetric). The self-supporting membrane can be backflushed to maximize the
efficiency of the crossflow filtration process. This operating feature, combined with
chemical stability, ensures reliability and long life expectancy. The hollow fiber
geometry allows a high membrane surface area to be contained in compact modules providing
high capacity while utilizing minimal space.

| Solutions | |
|
Products |
| Locations | |
|
Web Links |
| Technical Information | |
|
Application Questions |
| News Releases | ![]() |
![]() |
Material
Safety Data Sheets - Kochkleen Cleaners |
|
Please send comments to: Koch Membrane Systems, Inc.
|
|||
From:
U. S. Department of Agriculture, Rural Development Programs
http://www.usda.gov/rus/water/ees/englib/pdf/idwrt1.pdf
DESCRIPTION OF PROBLEM/ISSUE:
An old privately owned system serving four communities was declining in quality and the owner did not want to make improvements. USDA - Rural Development provided financing for purchase of the infrastructure, replacement of many leaking mains, raw water intake replacement after damaging floods, and filtration of water from creeks above the Cities of Wallace and Mullen. The District agreed to an aggressive program to install individual water meters to discourage wasteful demand. The system previously only chlorinated the creek water and thus did not meet the Surface Water Treatment Rule. They were under a consent order with the State.
The District wanted a system that would meet the proposed Cryptosporidium rule. The creek water usually has low turbidity except during Spring runoff. The State Division of Environmental Quality doesn't care for rapid sand filtration for small communities due to the lack of full-time qualified operator attention. Also, regarding slow sand filters, there was concern about how much surface area would be required to have cleaned and ripened cells available when using waters that sometimes have high turbidity. In the District, SS filters would have to be located in the river valley floor to have enough level land, and the filtered water pumped to pressurize the system.
SOLUTION:
The District now has on-line the first membrane filters financed by USDA - RD in Idaho. These are expected to provide very high if not the highest quality potable water available in the State, water without high dissolved solids and with virtually all the microscopic cysts and bacteria, most of the viruses, and larger organic molecules consistently removed with minimal operator attention and reduced THM's. Memtec by Memcor, (microfiltration) and Koch (ultrafiltration) were prequalified to bid. Koch was the successful bidder. The low bidder was required to run a pilot test for a set lump sum. After a successful pilot, a second step contract for equipment and installation oversight was awarded. The construction cost of the plants (piloting, equipment, plumbing, electrical, and buildings on small sites in steep terrain above the towns) was $2,970,000 for the 2 MGD and the 0.8 MGD plants. Plant startup began in January 1998 and information to date indicates they are performing satisfactorily.